NP-GRSM (10N(1) AND 10N(2) THE PROJECT CONSISTS OF REHABILITATING APPROXIMATELY 2.44 MILES OF NEWFOUND GAP ROAD FROM MP 12.32 TO MP 14.76 AND RESURFACING APPROXIMATELY 6.18 MILES OF NEWFOUND GAP ROAD FROM MP 6.14 TO MP 12.32, INCLUDING PARKING AREAS

DEFINITIVE CONTRACT won by BRYANT'S LAND AND DEVELOPMENT INDUSTRIES, INC. · work in COSBY, TN
$8,565,053
RecipientBRYANT'S LAND AND DEVELOPMENT INDUSTRIES, INC. UEI Y4ZPM3CNMSQ6
Award ID693C7321C000004
Award amount$8,565,053
Award typeDEFINITIVE CONTRACT
Awarding agencyDepartment of Transportation — Federal Highway Administration
NAICS237310 — HIGHWAY, STREET, AND BRIDGE CONSTRUCTION
PSCY1LB
Set-asideSmall business
Start dateDec 15, 2020
End dateMar 31, 2023
Place of performanceCOSBY, TN
Record updatedJun 16, 2022

View the official award record

More awards won by BRYANT'S LAND AND DEVELOPMENT INDUSTRIES, INC.

PROJECT NP-GRSM 10N(3), 19(1), 107(1): SCHEDULE A - LAKEVIEW DRIVE EAST (SWAIN COUNTY, NC). WORK INCLUDES PERFORMING FULL DEPTH RECLAMATION WITH CEMENT STABILIZATION AND CONSTRUCTING ASPHALT CONCRETE PAVEMENT OF 6.41 MILES OF LAKEVIEW DRIVE EAST AN
Department of Transportation · $29,698,622 · May 25, 2023
PROJECT NC NP BLRI 2K13; NC NP BLRI 2K14 THE PROJECT CONSISTS OF HURRICANE DAMAGE REPAIRS AT MP 316.4, 325.8 AND 325.9. THE WORK INCLUDES BRIDGE RAIL REPLACEMENT CONCRETE REPAIR, RIPRAP PLACEMENT, PAVEMENT RECONSTRUCTION, PAVEMENT MARKINGS, CULVER
Department of Transportation · $17,007,296 · Jan 6, 2026
PROJECT NP-GRSM 11(4): THE WORK IN SCHEDULE A INCLUDES THE REPLACEMENT OF THE TUNNEL DRAINAGE SYSTEM AND CHASES, REPAIRING CRACKED, SPALLED, AND DELAMINATED AREAS OF THE TUNNEL WALL, PERMANENT PAVEMENT MARKINGS, WALL DELINEATORS, DRAINAGE IMPROVEM
Department of Transportation · $9,821,057 · Aug 23, 2022
PROJECT NP SER PMS FY18(1) THE PROJECT CONSISTS OF PAVEMENT PRESERVATION TREATMENT IN CAPE HATTERAS NATIONAL SEASHORE, FORT RALEIGH NATIONAL HISTORIC SITE, AND WRIGHT BROTHERS NATIONAL MEMORIAL. THE WORK INCLUDES THIN ASPHALT PAVEMENT OVERLAY, CHIP SEAL, MICRO SURFACING, ASPHALT PAVEMENT MILLING, FULL-DEPTH ASPHALT PATCHING, CRACK CLEANING AND SEALING, PAVEMENT MARKING INSTALLATION, AND OTHER MISCELLANEOUS WORK.
Department of Transportation · $8,424,447 · Mar 13, 2019
PROJECT NP BISO 10(2): THE PROJECT CONSISTS OF THE RESURFACING OF APPROXIMATELY 7.6 MILES OF THE LEATHERWOOD FORD ROAD, INCLUDING THE RESURFACING OF THE BANDY CREEK BRIDGE AND CUMBERLAND RIVER BRIDGE. THE WORK INCLUDES ASPHALT PAVEMENT MILLING, FUL
Department of Transportation · $8,230,877 · May 28, 2020