TRANSFORMERS FOR MAURINE, FORT THOMPSON, & WATFORD CITY SUBSTATIONS

DEFINITIVE CONTRACT won by G & RK CONSULTING ASSOCIATES LLC · work in LITTLETON, CO
$4,044,268
RecipientG & RK CONSULTING ASSOCIATES LLC UEI GDVCAY1FZKL6
Award ID89503421CWA000055
Award amount$4,044,268
Award typeDEFINITIVE CONTRACT
Awarding agencyDepartment of Energy — Department of Energy
NAICS335311 — POWER, DISTRIBUTION, AND SPECIALTY TRANSFORMER MANUFACTURING
PSC6120
Set-aside8(a)
Start dateSep 28, 2021
End dateJun 28, 2024
Place of performanceLITTLETON, CO
Record updatedJan 27, 2023

View the official award record

More awards won by G & RK CONSULTING ASSOCIATES LLC

TRANSFORMER FOR FT2
Department of Energy · $4,993,363 · Jun 25, 2025
SIOUX CITY 2 KU1A AUTOTRANSFORMER REPLACEMENT
Department of Energy · $4,111,483 · Sep 27, 2021
MOBILE TRANSFORMER (MOBT27) - 115/69/34.5KV 40 MVA MOBILE TRANSFORMER WITH POWER TRANSFORMER, SURGE ARRESTERS, INSULATING OIL, AND ACCESSORIES, MOUNTED ON A SINGLE HIGHWAY TYPE SEMI-TRAILER.
Department of Energy · $3,925,683 · Sep 26, 2023
NDMO MOBILE SUBSTATION 115X69-12.47KV
Department of Energy · $2,000,497 · Sep 29, 2021
GROTON SUBSTATION TRANSFORMER, 3-PHASE, 115-69KV, 30/40/50 MVA
Department of Energy · $1,438,597 · Sep 27, 2022